PROJECTED BUILDING TIMELINE
APRIL 17-21, 2017
SURVEY COMPLETED
APRIL 24-28, 2017
COMPLETED SURVEY TO BUILDER
*BUILDER GOES TO COUNTY TOWN HALL AND SCHEDULES PUBLIC HEARING. HEARING SCHEDULE IS UP TO COUNTY. (TWO TO FOUR WEEKS)
*IF PUBLIC HEARING IS NOT CHALLENGED, BUILDER WILL FINALIZE BUILDING PLANS.
*ONCE BUILDING PLANS ARE FINALIZED, THE REST OF THE INTERNAL DRAWINGS ARE COMPLETED: PLUMBING, ELECTRICAL, HAVAC, KITCHEN ETC.
*ONCE ALL DRAWINGS ARE COMPLETED, BUILDER PRESENTS ALL PLANS TO THE COUNTY FOR FINAL APPROVAL.
* WHEN COUNTY GIVES FINAL APPROVAL (TWO TO FOUR WEEKS), BUILDING IS ORDERED BY BUILDER (FOUR TO EIGHT WEEKS)
*BUILDER COMMENCES POST DEMO
*BUILDER COMMENCES SLAB FABRICATION WHILE WAITING FOR BUILDING TO COME IN.